After the work of the barite milling production line is completed, the barite grinding mill equipment should be regularly cleaned and maintained, so that the production line equipment should be kept in an optimal state of use.
1. Start the bucket elevator;
2. Start the jaw crusher;
3. Start the analyzer after the material is stored in the silo;
4. Start the blower (empty load start, then load after normal operation); The host computer starts the electromagnetic vibrating feeder immediately after starting the host.
At this point the grinding work is the beginning. The simple sequence of operation sequence is as follows: start: hoist → crusher → analyzer → fan → host → feeder. |
|